Deferred Submittals Process

bcgovias

SUBJECT:   Process for accepting deferred submittals –

The process for accepting deferred submittals is per section of the IBC pertaining to deferred submittals. Currently we are enforcing IBC-2012, and section 107.3.4.1 pertaining to deferred submittals.

Section 107.3.4.1 of the IBC-2012 states the following;

 Deferred submittals. For the purposes of this section, deferred submittals are defined as those portions of the design that are not submitted at the time of the application and that are to be submitted to the building official within a specified period.

Deferral of any submittal items shall have the prior approval of the building official. The registered design professional in responsible charge shall list the deferred submittals on the construction documents for review by the building official

Documents for deferred submittal items shall be submitted to the registered design professional in responsible charge who shall review them and forward them to the building official with a notation indicating that the deferred submittal documents have been reviewed and found to be in general conformance to the design of the building.

The deferred submittal items shall not be installed until the deferred submittal documents have been approved by the building official.